EXECUTIVE SUMMARY - 4 PHASES

  1. Main Building
  2. 7 x Jungle Homes
  3. Wellness Facilities
  4. Community integration, offerings and activation of space

PHASE 1: MAIN BUILDING COMPLETION

(Current - Q2 2025)

Current Status: 90% Complete as of Nov 1, 2024

Completion Timeline:

  • Building Construction Complete: January 1, 2025
  • Interior Finishing: January - March 2025
  • Systems Integration: February - March 2025
  • Fully Functional: April 1, 2025 (Q2 2025)

Key Milestones:

  1. Building completion (January 1, 2025)
  2. Interior furnishing (March 1, 2025)
  3. Staff training begins (March 15, 2025)
  4. Soft opening preparations (March 30, 2025)
  5. Operational launch (April 1, 2025)

PHASE 2: JUNGLE HOMES DEVELOPMENT

Current Status: 10% Complete

(Current - Q4 2025)

Construction Timeline:

  • Construction Period: November 2024 - July 1, 2025
  • Interior Design & Finishing: July - September 2025
  • Landscaping & Integration: August - September 2025
  • Fully Functional: October 1, 2025

Key Milestones:

  1. Construction completion (July 1, 2025)
  2. Interior completion (September 1, 2025)
  3. Landscape integration (September 15, 2025)
  4. Systems testing (September 20-30, 2025)
  5. Ready for occupancy (October 1, 2025)

PHASE 3: WELLNESS FACILITIES & AMENITIES

(Current - Q4 2025)

The SOL Experience: 12 Integrated spaces
12 part Comprehensive SOL Experience List Overview * Unique venue with 7 private jungle homes complementing the SOL space * Integrated design for seamless flow, connection, and wisdom sharing Stay Options 1. Luxury Jungle Homes * High-end, private accommodations * Seamless blend with Balinese jungle environment 2. SOL Rooms & Co-living Spaces * Comfortable rooms in

Development Timeline:

  • Construction: November 2024 - July 1, 2025
  • Equipment Installation: July - August 2025
  • Testing & Certification: August - September 2025
  • Fully Operational: October 1, 2025

OPERATIONAL TIMELINE

Q4 2024 - Q1 2025:

  • Main building completion
  • Initial staff recruitment
  • Systems development
  • Marketing launch

Q2 2025 (April 1):

  • Main building operational
  • Basic services launch
  • Staff training complete
  • Initial community programs

Q3 2025 (July 1):

  • Jungle Homes finishing
  • Wellness facilities installation
  • Program development
  • Community building

Q4 2025 (October 1):

  • Jungle Homes operational
  • Wellness facilities active
  • Full program launch
  • Community integration

Q1 2026 (January 1):

  • Full facility operation
  • Complete program offering
  • Established community
  • Global marketing expansion

INVESTMENT OPPORTUNITIES

SOL | Exclusive Invitation to Invest & Partner
SOL Bali: Jungle Homes Investment Opportunity “Invest in Transformation, Reap Holistic Returns” APPLY TO PARTNER HERE kami@marcilock.com Kami : ‪+1 (801) 631‑0729‬ Brief overview of The SOL concept The SOL Bali: A Visionary Space for Transformation and Conscious Living The SOL Bali - (Sanctuary of Light) is a

Current Phase (Limited Time):

  • Pre-completion pricing
  • Founding Member benefits
  • Priority selection
  • Maximum ROI potential

Next Phase (Q2 2025):

  • Early occupancy options
  • Enhanced benefits
  • Community influence
  • Established pricing

Final Phase (Q4 2025):

  • Market rate pricing
  • Standard benefits
  • Full facility access
  • Community membership